TotalEnergies has committed to Net Zero by 2050. Transformation of retail service stations into multi-energy hubs is critical to this strategy.

The challenge: Standardizing solar deployment across hundreds of unique sites with varying layouts, while adhering to strict petrochemical safety standards (HSSE).

SCALE
NATIONAL
SAFETY STANDARD
PETRO-CHEM
TIMELINE
ACCELERATED
"We aren't just selling fuel anymore. We are providing energy solutions. Our stations must reflect that transition."
— SUSTAINABILITY LEAD
02
SECTION

THE SOLUTION

In4solar developed a Modular Solar Carport & Rooftop Solution that can be rapidly deployed and scaled. with an average system size of 27kW per site. This approach allows for standardised engineering and permitting, drastically reducing rollout time.

12
Sites Deployed
Rapid rollout capability across the network
ZERO
HSSE Incidents
Flawless safety record in high-risk zones
35%
Energy Reduction
Average grid dependency reduction per site
Standardised Designs
Pre-approved engineering templates for rapid municipal approval
ATEX Compliance
Equipment certified for use in potentially explosive atmospheres
Brand Integration
Structures designed to enhance the visual identity of the station
Project Scope

FEATURED DEPLOYMENTS

Key installations across the 27kW average portfolio, showcasing the versatility of the modular solution.

SITE 01
TotalEnergies Lukhanji
GRID-TIED~27kWp
SITE 02
TotalEnergies Despatch
GRID-TIED~27kWp
SITE 03
TotalEnergies Roedtan
GRID-TIED~27kWp
SITE 04
TotalEnergies Sandvale
GRID-TIED~27kWp
SITE 05
TotalEnergies Sedgefield
GRID-TIED~27kWp
SITE 06
TotalEnergies Kingsway
GRID-TIED~27kWp
SITE 07
TotalEnergies Summerstrand
GRID-TIED~27kWp
SITE 08
TotalEnergies Table View
GRID-TIED~27kWp
SITE 09
TotalEnergies Woodstock
GRID-TIED~27kWp
SITE 10
TotalEnergies Norkem Park
GRID-TIED~27kWp
SITE 11
TotalEnergies Pellissier
GRID-TIED~27kWp
SITE 12
TotalEnergies Cannon Hill
GRID-TIED~27kWp
Network Impact

324 kWp

INSTALLED

12
Key Sites
25yr
Lifespan
-35%
Grid Use

CLEAN ENERGY

CARBON REDUCTION
480t
Annual CO2 emissions avoided
ENERGY GENERATED
530MWh
Clean energy produced annually
BRAND IMAGE
NET ZERO
Tangible progress towards 2050 goals
SITE EFFICIENCY
HIGH
Reduced operational costs per site
Solar Farm Background

Scale your operations with In4solar.

Request a technical feasibility study for your facility and discover how our engineering can transform your operational efficiency.

01/08
The Motivation

What is your primary energy goal?

FacebookDownload Company Profile